37 Captive & Commercial Mines Under Production; 11 New Mines Likely to Start Production This Year
• Anil Mathur
New Delhi 6 Sep.
Coal
production from coal blocks during April-August for the fiscal 2022-23 has been
reviewed by the Additional Secretary & Nominated Authority, of the Ministry
of Coal, in the presence of project proponents. Coal production achieved during
April-August, 2022-23 is 43.93 million ton which is 57.74 % higher than 27.85
million ton coal produced during the same period 2021-22.
Two
mines auctioned in 2021 under commercial auction reforms have become
operational and produced 2.36 million ton coal in April-August, 2022-23. At
present, 37 captive and commercial mines are under production and it is
expected that at least 11 more new mines will start production during the year.
This will significantly contribute to meet coal demand in the country.
The
Ministry appreciated the efforts of coal blocks allocattees in attaining such
high growth and hopeful that the target production of 141.78 million ton from
these coal blocks during FY 2022-23 will be achieved.
At
the same time, it was noted with concern that Parsa East & Kanta Basan coal
block production has stopped and Parsa coal block production has not started.
Continued stoppage may adversely impact achievement of target this year.
Further,
during the review, project proponents shared the efforts made by them and the
challenges faced. Ministry of Coal assured to extend all possible support in
resolving the issues.